Water Sector – City Investment Plan

 

Activity

Amount in Financial Years (Crore)

JNNURM

05-06

06-07

07-08

08-09

09-10

10-11

11-12

Total

GOI

GOK

IR/IF

Total

Comprehensive Water Sector Development Master Plan

0

8

150

150

 

 

 

308

154

61.6

92.4

308

Energy Audit Studies

0

8

150

150

 

 

 

308

154

61.6

92.4

308

Water Quality Studies and Monitoring

0

8

150

100

50

50

50

408

204

81.6

122.4

408

Design and Implementation of Communication Strategy

0

10

100

100

100

75

75

460

230

92

138

460

Baseline Survey

0

 

75

 

 

 

 

75

37.5

15

22.5

75

Human Resources Development

0

10

100

200

200

175

150

835

417.5

167

250.5

835

Establishment of Regulatory Authority

0

10

75

150

150

150

150

685

342.5

137

205.5

685

GIS Mapping of Water and Sewerage Utility Mapping

0

 

100

200

50

50

50

450

225

90

135

450

Community Initiatives Support

0

 

50

50

50

50

 

200

100

40

60

200

Modernizing Financial Management and MIS

0

75

100

100

100

 

 

375

187.5

75

112.5

375

E-Governance

0

 

60

60

60

60

60

300

150

60

90

300

Total

0

129

1110

1260

760

610

535

4404

2202

880.8

1321.2

4404

Protection of river sources , Periyar and Muvattupuzha rivers

0

10

12.5

0

0

0

0

22.5

11.25

4.5

6.75

22.5

Construction of Intake arrangements at Aluva

0

0

50

200

200

50

0

500

250

100

150

500

Construction of Intake arrangements at Pazhoor

0

0

25

50

 

 

 

75

37.5

15

22.5

75

Construction of 100 mld  Water Treatment plant at Maradu

0

0

250

500

600

300

 

1650

825

330

495

1650

Construction of 285 mld Water Treatment Plant at Kalamassery

0

0

300

500

800

900

450

2950

1475

590

885

2950

Total

0

10

637.5

1250

1600

1250

450

5197.5

2598.8

1039.5

1559.25

5197.5

Laying Raw Water Pumping Mains

0

000

2000

2000

2400

3600

4874

14874

7437

2974.8

4462.2

14874

Laying Clear Water Pumping Mains

0

 

800

609

500

600

500

3009

1504.5

601.8

902.7

3009

Construction of GL sumps and service reservoirs

0

 

 

863

1500

756

200

3319

1659.5

663.8

995.7

3319

Construction of Electrical Sub-station and Pump Houses

0

 

130

300

400

300

300

1430

715

286

429

1430

Supply and Erection of Pump sets

0

 

63

300

300

300

200

1163

581.5

232.6

348.9

1163

Laying transmission mains and rehabilitation of existing distribution system

0

 

 

400

500

500

400

200

2000

1000

400

600

2000

Laying additional distribution net works

0

 

500

9800

9800

19900

20000

60000

30000

12000

18000

60000

Total

0

0

3893

14372

15400

25856

26274

85795

42898

17159

25738.5

85795

a) SCADA Project

0

 

830

1250

1250

1660

1660

6650

3325

1330

1995

6650

b) UFW Reduction Project

0

 

800

1200

1200

1990

1990

7180

3590

1436

2154

7180

c) 24 Hr. Water Supply Project

0

 

920

1380

1380

1840

1840

7360

3680

1472

2208

7360

Total

0

0

2550

3830

3830

5490

5490

21190

10595

4238

6357

21190

1. O & M of Water Supply system

0

 

 

 

 

 

 

 

 

 

 

 

a) Motor & Electrical repairs and upgradation

0

 

18

0

0

0

0

0

18

9

3.6

5.4

18

b) Distribution network reforms rationalization

0

 

0

80

170

34

0

10

294

147

58.8

88.2

294

Total

0

18

80

170

34

0

10

312

156

62.4

93.6

312

Citizen feed back mechanisms to be established

0

3

65

65

65

0

0

198

99

39.6

59.4

198

Modernization of Complaint redressal  system

0

3

65

65

0

0

0

133

66.5

26.6

39.9

133

Total

0

6

130

130

65

0

0

331

165.5

66.2

99.3

331

Grand Total

0

163

8400.5

21012

21689

33206

32759

117230

58615

23446

35168.9

117230

The total project cost is worked out to 1172 .30 crores.

 

 

 

Water Supply Sector - Strategy (2006-2011) 

Component

Activity

Year

1

Year

 2

Year

 3

Year

 4

Year

5

Year

 6

Year

7

Planning, Reforms and Institutional Strengthening

Comprehensive Water Sector Development Master Plan

 

 

 

 

 

 

 

Energy Audit Studies

 

 

 

 

 

 

 

Water Quality Studies and Monitoring

 

Design and Implementation of Communication Strategy

 

Baseline Survey

 

 

 

 

 

 

 

Human Resources Development

 

 

 

 

Establishment of Regulatory Authority

Proposed scheme is augmentation  of the existing one under KWA

GIS Mapping of Water and Sewerage Utility Mapping

 

 

 

 

 

 

Community Initiatives Support

 

 

 

 

 

 

Modernizing Financial Management and MIS

 

 

 

 

E-Governance

 

Water Resource Management

Protection of river sources , Periyar and Muvattupuzha rivers

 

Construction of Intake arrangements at Aluva

 

 

 

 

Construction of Intake arrangements at Pazhoor

 

 

 

 

Construction of 100 mld  Water Treatment plant at Maradu

 

 

 

 

Construction of 285 mld Water Treatment Plant at Kalamassery

 

 

 

Augmentation of Water Supply

Laying Raw Water Pumping Mains

 

 

 

Laying Clear Water Pumping Mains

 

 

 

Construction of GL sumps and service reservoirs

 

 

Construction of Electrical Sub-station and Pump Houses

 

 

Supply and Erection of Pump sets

 

 

 

 

Laying transmission mains and rehabilitation of existing distribution system

 

 

Laying additional distribution net works

 

 

Service Delivery

a) SCADA Project

 

b) UFW Reduction Project

 

c) 24 Hr. Water Supply Project

 

Governance

1. O & M of Water Supply system

 

 

 

 

 

 

 

a) Motor & Electrical repairs and upgradation

 

 

 

b) Distribution network reforms rationalization

 

Citizens Relations Management

Citizen feed back mechanisms to be established

 

 

 

 

Modernization of Complaint redressal  system